Examples of grounding solutions

Examples of grounding solutions

on the base of using ZANDZ and GALMAR

Object name
Customer
 

 

Equipment applied
 

 

Implementation date
 

 
Baksan HPP RusHydro 41 set of ZANDZ ZZ-100-102 2012
Communication objects  in the Far East Rostelecom, hub brunch "Far East" about 150 set of ZANDZ ZZ-000-030 +  30 sets of ZANDZ ZZ-000-636 2008-2013,
Cross-connect equipment in the territoru of The Central Federal District Rostelecom, hub brunch "Center" about 850 sets of ZANDZ ZZ-000-015 (individual kitting) 2011-2013,
Infrastructure of Olympic Games objects in 2014:Power substation, administrative and residential buildings. OlimpStroy 6500 GL-00085 ground rods with additional parts for mounting +  36 kits of ZANDZ ZZ-100-102 2012-2013,
 Railway objects  at the site "Anchor Chain - Dagomys":power and telemetry equipment Russian Railways 16 000 ground rods GL-10012 and GL-10022 with additional parts for mounting 2013
Railway objects at the site "Aldan-Neryugri cargo":power and telemetry equipment Railways of Yakutia 53 kits  of ZANDZ ZZ-100-102 2012
Diesel-generator kits at the railway stations of the republic. Sakha (Yakutia):Taiga, Aldan, Tommot, Amga, Hanierdah, Kerdem Transtelekom 53 kits  of ZANDZ ZZ-100-102 2012-2013,
Seasonal enrichment facility of Elga mining processing plant Yakutugol,  "Mechel" JSC 40 kits of ZANDZ ZZ-100-102 2012
Intermediate-active oil products storages for the needs of compressoion plants as part of construction projects "The system of Bovanenkovo - Ukhta main gaslines" Gazprom 160 kits of ZANDZ ZZ-100-102 2012
TK "Turquoise Katun" TK "Turquoise Katun" 32 kits  of ZANDZ ZZ-100-102 2010-2012,
Various objects of VankorNeft VankorNeft 42 kits  of ZANDZ ZZ-100-102 2011-2013,
Amplifying equipment of RTRS Krasnoyarsk  RTRS Krasnoyarsk 7 kits of ZANDZ ZZ-100-102 2010
Amplifying equipment of RTRS Irkutsk RTRS Irkutsk 10 sets ZANDZ ZZ-000-015 2009
Various objects  Arsenyev Aviation Company "Progress" to the name of. N.I. Sazykin 35 sets of ZANDZ ZZ-000-015 2011
The river station complex in Salekhard (Yamalo-Nenets District) The river station complex in Salekhard (Yamalo-Nenets District) 8 kits of ZANDZ ZZ-100-102 2013

Customer: RusHydro

Customer: RusHydro
The picture is granted by the press-service of "RusHydro" JSC

Date of implementation: 2012

Description: 41 kit  of electrolytic grounding ZANDZ ZZ-100-102 for stony soils.

Grounding of some equipment (including diagnostic) at the Baksan hydroelectric power station in stony and rocky soils.

On the average, one grounding device consisted of 6-7 sets of ZZ-100-102. Earth resistance is less than 4 ohms.

Reviews:

Customer RusHydro-1   Customer RusHydro-2

Customer RusHydro-3   Customer RusHydro-4


Customer: Rostelecom, hub brunch "Far East"

Customer: Rostelecom, hub brunch

Date of implementation: 2008-2013,

Description: About 150 sets of universal modular grounding kits ZANDZ ZZ-000-030 (Installation in the form of 3-electrode 10 meters each) and 30 sets of specialized modular grounding kits ZZ-000-636 for container objects.

Grounding of electrical equipment on connection objects, including container, in the Far East, incl. Sakhalin region with rocky soils.

Kits ZZ-000-030 are used because of their versatility. One deep-laid electrode (10 meters) from the kit was used for one object.Thus, one kit was enough for 3 of the object, which saved money.

The grounding resistance less than 4 ohms and less than 10 ohms (depending on the equipment and the object).

Customer: Rostelecom, hub brunch


Customer: Rostelecom, hub brunch "Center"

Customer Rostelecom, hub brunch Center

Date of implementation: 2011-2013,

Description: About 850 module grounding kits ZANDZ ZZ-000-015 with the modified set - the number of accessories needed for installation was reduced.

Cross equipment grounding (Intradistrict crosses) in the territory of the Central Federal District.

Earth resistance 4 ohm or 10 ohm.


Customer: OlimpStroy

Customer OlimpStroy

Date of implementation: 2012-2013,

Description: 6500 grounding rods GL-00085 (1.5 meters long) with additional parts for mounting   + 36 kits  of electrolytic grounding ZANDZ ZZ-100-102.

Grounding for the infrastructure of the Olympic Games 2014 in Sochi: Power substations (90 substations of different types) (including ССTS), administrative and residential buildings.

Electrolytic пrounding was used on objects with stony and rocky soils.

Customer OlimpStroy-1

Reviews:

Customer: OlimpStroy-2


Customer: Russian Railways

Customer Russian Railways

Date of implementation: 2013.

Description: About 16,000 grounding rods GALMAR GL-10012 (1.5 m long and 14 mm in dimeter) and GL-10022 (1.5 m long and 17 mm in diameter) with additional mounting parts.

Grounding for railway objects at the site "Anchor Chain - Dagomys": power and telemetry equipment.

During the preparation for the  Olympic Games 2014 in Sochi, "Russian Railways" JSC carries out serious work on building of a modern railway infrastructure on the Black Sea coast, in order to ensure the receipt of cargos to the Olympic facilities under construction, as well as to increase passenger traffic of participants and guests of the Olympiad.

Customer Russian Railways-1


Customer: Railways of Yakutia

Customer Railways of Yakutia

Date of implementation: 2012

Description: 53 kits of electrolytic grounding ZANDZ ZZ-100-102.

Grounding for railway objects at the site "Aldan - Neryungri Cargo": power and telemetry equipment, frozen ground conditions.

Customer Railways of Yakutia-1

Reviews:

Customer Railways of Yakutia-2   Customer Railways of Yakutia-3


Customer: Transtelekom

Customer Transtelekom

Date of implementation: 2012-2013,

Description: 53 kits of electrolytic grounding ZANDZ ZZ-100-102.

Grounding of diesel-generator units at the railway stations of the  republic. Sakha (Yakutia):

  • Taiga;
  • Aldan;
  • Tommot;
  • Amga;
  • Hanierdah;
  • Kerdem

in frozen ground conditions.

Customer Transtelekom-1

Reviews:

Customer Transtelekom-2


Customer: Yakutugol, "Mechel" JSC

Customer Yakutugol Mechel JSC
The photo is granted by the press-service of the "Mechel" JSC

Date of implementation: 2012

Description: 40 kits of electrolytic grounding ZANDZ ZZ-100-102.

Grounding of some equipment (including external lightning protection systems) of seasonal concentration plant of Elga mining and processing plant in the  frozen soil conditions.

Customer Yakutugol Mechel JSC-2
The photo is granted by the press-service of the "Mechel" JSC


Customer: Gazprom

Customer Gazprom

Date of implementation: 2012

Description: 160 kits of electrolytic grounding ZANDZ ZZ-100-102.

The grounding devices as a part of the external and internal lightning protection of intermediate-active oil storage for the needs of the compressor stations  as a part of construction project "The system of main gaslines Bovanenkovo-Ukhta":

  • CS-5 "Usinskaya";
  • CS-6 "Intinskaya";
  • CS-7 "Syninskaya";
  • CS-8 "Chikshinskaya";
  • CS-9 "Maloperanskaya"

in frozen ground conditions.

Customer Gazprom-1


Client: TK "Turquoise Katun"

Client TK Turquoise Katun

Date of implementation: 2010-2012,

Description: 32 kits of electrolytic grounding ZANDZ ZZ-100-102.

Ground TS, electrical systems and external lightning protection in stony soil conditions.

Client TK Turquoise Katun-1


Customer: VankorNeft

Customer VankorNeft

Date of implementation: 2011-2013,

Description: 42 kits of electrolytic grounding ZANDZ ZZ-100-102.

Grounding of various types of objects (including objects as part of the external lightning protection system) in frozen ground conditions.

Customer VankorNeft-1


Customer: RTRN Krasnoyarsk

Customer RTRN Krasnoyarsk

Date of implementation: 2010

Description: 7 kits of electrolytic grounding ZANDZ ZZ-100-102.

Grounding of amplifying equipment in conditions of rocky soil with a ground resistance of less than 2 ohms.


Customer: RTRN Irkutsk

Customer RTRN Irkutsk

Date of implementation: 2010

Description: 10 modular grounding kits ZANDZ ZZ-000-015.

Grounding amplifying equipment in sandy soil conditions. Deep-laid electrodes "pierced" a sandy hill on which the object is placed, penetrating into water-saturated soil layers, thus ensuring a low (less than 4 ohm) earth resistance.


Customer: Arsenyev Aviation Company "Progress" to the name of  N.I. Sazykin

Customer Arsenyev Aviation Company Progress to the name of  N.I. Sazykin

Date of implementation: 2011

Description: 35 modular grounding kits ZANDZ ZZ-000-015.

Grounding of various types of objects, including objects as parts of external lightning protection systems.

Customer Arsenyev Aviation Company Progress to the name of  N.I. Sazykin-1


Customer: River station complex in Salekhard (Yamalo-Nenets District)

Customer River station complex in Salekhard (Yamalo-Nenets District)

Date of implementation: 2013.

Description: 8 kits of electrolytic grounding ZANDZ ZZ-100-102.

Grounding of electrical equipment in the conditions of frozen and rocky soils for the construction of a new river station, which will centralize transportation - the port will be used for all types of vessels.

Customer River station complex in Salekhard (Yamalo-Nenets District)-1


Related Articles: